planeus offers handy Gantt chart tools to help you fine-tune your schedule and keep your production running smoothly.

# Solving Conflicts in Gantt Chart

In the **Order Gantt View**, you can click a Work Step and choose:

- **Fill in Gaps left**
- **Fill in Gaps right**

![](https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/ZH_OxTtisNi5RbVLgBw4Z_image.png)

This will shift the selected Work Step as far as it can go left or right, until:

- It touches or overlaps with the previous Work Step.
- The Resource has no more capacity during the new time slot.

![](https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/EBuMSzVBdqyoipx8Hw0lF_2025-07-09-17-38-04.gif)

### Plan Conflictless for Successors

In the **Resource Gantt View**, you can select a Work Step and schedule all successor Work Steps **forward without Resource conflicts**.
*Plan Conflictless for Successors&#x20;*&#x6D;eans that this rescheduling is applied on **only the successing Work Steps of your chosen Work Step.&#x20;**&#x54;he selected Work Step itself and all previous Work Steps remain **unchanged**.

![](https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/TyDRA-7kspg9hbYW3x5B-_image.png)

This rescheduling will remove all **Resource conflicts**, tasks may be moved later, **even if these exceed the predefined delivery date.**

::Image[]{src="https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/yUeV-j4hA9wjLEROJPTrg_2025-07-09-17-44-34.gif" size="62" width="416" height="280" position="flex-start" showCaption="false"}

### Plan Conflictless from Here

*Plan Conflictless from here&#x20;*&#x6D;eans that this rescheduling is applied **starting at the current point in the plan**, excluding what was scheduled before this time.

![](https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/vvkGoQ1a-8ZtU3UXkWkka_image.png)

All tasks that are planned **after this point&#x20;**&#x77;ill be scheduled so that no machine or person is used at the same time.&#x20;

This rescheduling will remove all **Resource conflicts**, tasks may be moved later, **even if these exceed the predefined delivery date.**

# Free Move

The **Free Move** option lets you move a Work Step freely, ignoring the usual predecessor-successor relationships defined in the Technology.&#x20;

:::hint{type="info"}
You can enable and disable the Free Move feature on or off under **Administration > Settings**.
:::

# Optimize Utilization in Resource Gantt chart

In the **Resource Gantt View**, you can optimize how work is arranged on a resource:

This tool:

- Closes gaps between Work Steps.
- Removes unnecessary overlaps.
- Re-orders Work Steps from left to right.

However:

- It only works when all Work Steps use the **same resource** across production orders.
- It stops if:
  - A production order uses **multiple resources**.
  - It hits a **paused Work Step**.

:::hint{type="info"}
The feature can’t be used with resources marked as “Allow Multi-Assignment.”
:::

# Locking / Fixing Production Order &#x20;

## Why is there a lock icon?

A **lock icon** in the Gantt Chart means that Production Order is locked and cannot be moved in the schedule.

If you want to **lock a Production Order and its Work Steps** in place:

1. Right-click the Production Order.
2. Choose **Lock Production Order**.

::Image[]{src="https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/wfm7R6uw8JrIIAcn_oLJa_image.png" size="62" width="442" height="129" position="flex-start" showCaption="false"}

Now the Production Order is **locked** and **cannot be moved**.

::Image[]{src="https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/8Fm62DI11-kKaPk3psIqc_image.png" size="62" width="390" height="69" position="flex-start" showCaption="false"}

## How to unlock a production order?

You can right-click again to **unlock&#x20;**&#x61; Production Order if you need to make changes.&#x20;

::Image[]{src="https://api.archbee.com/api/optimize/M1QBpK9lJudQQL_d-GMK2/fZ1X2qilEY2kPud-mx1Ft_image.png" size="62" width="441" height="129" position="flex-start" showCaption="false"}

:::hint{type="success"}
planeus's Gantt chart tools will help you **adjust your plan quickly and safely**, keeping your schedule neat and your resources efficiently used.&#x20;
:::