Production Order Management
13 min
pausing production orders in the previous version , pausing was only possible for production orders with status "interrupted" the pausing production orders feature lets you temporarily stop the progress on production orders that have already started, without losing any progress or data what does "pausing" mean? when you pause a production order, planeus removes it from the active planning schedule all related work steps are paused as well paused work steps are not included in planning until you resume the order what data will be saved? any feedback already recorded for the paused production order stays saved when you resume the order later only the remaining quantity is scheduled again remaining quantity = target quantity minus any already confirmed quantities from feedback resumed work steps that already reached target yield quantity will be automatically marked as "completed" if the original technology included fixed dates , planeus ignores those when you resume the production order what’s the difference between unscheduling and pausing? it’s easy to mix up unscheduling and pausing here’s how they’re different unscheduling an order item unscheduling order item will deletes all related data , including production orders work steps processes feedback records use this if you haven’t started work yet and want to fully remove an order item from your plan pausing a production order keeps all data and their feedback safe and unchanged simply puts the production order on hold so you can resume it later without losing any data perfect for handling unexpected situations, like missing materials machine breakdowns changing priorities how to pause a production order? open the detail panel for the production order click pause production order paused production orders will be marked with a special symbol in the status column how to unpause a production order open the detail panel for the paused production order click unpause order when scheduing a unpaused order item, planeus will reschedule the production order forward from today or chosen start date plan only the remaining quantity for each work step when pausing and unpausing orders, assembly docid\ q0sfaieebpmtws5q08ev2 structure will be ignored reduce quantity when unpausing when you unpause a production order, you can reduce the order quantity this is useful when you do not want to continue the full original quantity, but only want to continue with a smaller amount how it works if quantity reduction is switched on, planeus will shows the require field new target quantity when quantity reduction is switched off, this field is hidden allowed quantity the new quantity must stay within these limits minimum 1 maximum original quantity minus 1 example if the original ordered quantity is 100, the highest possible new target quantity would be 99 if the production order quantity is 1 , you cannot reduce the quantity using this function suggested quantity when enabling quantity reduction, planeus will automatically suggest the new target quantity if feedback already exists, planeus uses the latest completed operation with feedback to suggest the new quantity you can change the suggested quantity manually within the maximum limit parallel work steps sometimes, several parallel work steps docid 5e4pjd vvyxlpkic3oha could be worked simultaneously by the same position number in this case, planeus will add their reported quantities together and uses this as the suggested quantity but still, the new quantity cannot be higher than the maximum limit changing quantities in production orders you can change the quantity directly in the production order’s quantity field when you change the quantity it will reschedule the production order delete all existing feedback adding multiple production orders to one process you can manually add additional production orders to an existing production process go to the detail panel under planning objects > processes add new production orders as needed this makes it easy to expand processes without starting over the pause production orders feature gives you the flexibility to temporarily stop work and pick it up again later — keeping your planning agile and your data safe fix production orders when scheduling fix production orders when scheduling if you turn on “fix production orders when scheduling” in the settings, every production order is locked as soon as it’s scheduled to move an production order, you first need unlock it manually for more, see locking / fixing production order docid 7ls4ff8z5 1z5 8egi tl