With this function, you can make sure that only jobs with the same requirements are processed together on one resource. Example: EU orders cannot be mixed with US orders on the same machine.
How Resource Programs work


Per Article (applies to all Work Steps of that Article)

or Per Work Step (based on the Resource selected)

If a Resource was not tied to any Resource Programs, all Resource Programs can be chosen.
Rules to remember
- If no Resource Program is set at item or Work Step level → the resource can run any job.
- A Work Step setting always beats an Article setting.
- An Article setting applies to all Work Steps, unless a Work Step has its own program.